NextDecade expects first LNG production at Rio Grande facility in H1 2027
Share
Listen to the news
NextDecade expects first LNG production at Rio Grande facility in H1 2027
  • NextDecade reaffirmed targets for Rio Grande LNG first gas in 2H 2026, first LNG from Train 1 in 1H 2027; project remains ahead of schedule.
  • Train 6 outlook: final Environmental Impact Statement due June 25, 2027; timing supports a final investment decision in 2H 2027.
  • Funding expectations supported by new debt: Phase 1 HoldCo Borrower $1 billion term loan at 7.05% due June 2033; Phase 1 LLC issued $3.5 billion senior secured notes.
  • Train 5 financing continues: 6.56% Senior Secured Notes due 2050 issued in $100 million tranches; $350 million outstanding as of July 30.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. NextDecade Corporation published the original content used to generate this news brief on July 30, 2026, and is solely responsible for the information contained therein.

Disclaimer:This article represents the opinion of the author only. It does not represent the opinion of Webull, nor should it be viewed as an indication that Webull either agrees with or confirms the truthfulness or accuracy of the information. It should not be considered as investment advice from Webull or anyone else, nor should it be used as the basis of any investment decision.
What's Trending
No content on the Webull website shall be considered a recommendation or solicitation for the purchase or sale of securities, options or other investment products. All information and data on the website is for reference only and no historical data shall be considered as the basis for judging future trends.