Gorilla Technology buys Thailand land site for planned 200MW AI data center campus
Share
Listen to the news
Gorilla Technology buys Thailand land site for planned 200MW AI data center campus
  • Gorilla Technology acquired land site in Korat, Thailand to develop planned 200MW AI data center campus.
  • Project targets 150MW net IT load for high-density GPU deployments across six data halls.
  • Construction slated to start July 2026, with first phase targeted for completion in Q1 2027, subject to approvals and financing.
  • Campus projected to generate about USD 1.5 billion in annualized revenue from 2028, contingent on customer contracting and utilization.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. Gorilla Technology Group Inc. published the original content used to generate this news brief on May 05, 2026, and is solely responsible for the information contained therein.

Disclaimer:This article represents the opinion of the author only. It does not represent the opinion of Webull, nor should it be viewed as an indication that Webull either agrees with or confirms the truthfulness or accuracy of the information. It should not be considered as investment advice from Webull or anyone else, nor should it be used as the basis of any investment decision.
What's Trending
No content on the Webull website shall be considered a recommendation or solicitation for the purchase or sale of securities, options or other investment products. All information and data on the website is for reference only and no historical data shall be considered as the basis for judging future trends.