International Tower Hill Mines publishes corporate presentation on Livengood gold project development

PUBT · 6d ago
International Tower Hill Mines publishes corporate presentation on Livengood gold project development
- International Tower Hill highlighted Livengood Gold Project in Alaska as one of largest undeveloped US gold assets advancing toward production.
- Project inventory included 9 million oz proven and probable reserves, 13.6 million oz measured and indicated resources.
- Pre-feasibility plan outlined 21-year mine life, 6.4 million oz gold production, 65,000 tons/day throughput.
- Cost profile in 2023 study used USD 1,680/oz gold price, showed life-of-mine AISC about USD 1,171/oz, initial capex about USD 1.93 billion.
- Company outlined development priorities spanning bankable feasibility work, permitting start, 3,000-meter drilling program, antimony byproduct evaluation.
Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. International Tower Hill Mines Ltd. published the original content used to generate this news brief on April 23, 2026, and is solely responsible for the information contained therein.
Disclaimer:This article represents the opinion of the author only. It does not represent the opinion of Webull, nor should it be viewed as an indication that Webull either agrees with or confirms the truthfulness or accuracy of the information. It should not be considered as investment advice from Webull or anyone else, nor should it be used as the basis of any investment decision.